An architect's area statement for a Pune parcel can carry two totals several thousand square metres apart: the built-up area that counts against FSI, and the covered area of everything that will actually be built, basements and parking floors included. In environmental clearance, real estate is measured on the second total. Item 8(a) of the EIA Notification, 2006 draws its line at 20,000 square metres of built-up area, and which total meets that line decides whether a project needs a state appraisal before a single trench is dug.

Key takeaways

  • Under the EIA Notification, 2006, building and construction projects of 20,000 to under 1,50,000 square metres of built-up area are item 8(a), and townships and area development projects of 50 hectares or 1,50,000 square metres of built-up area are item 8(b); both are Category B, decided at state level.
  • On 5 August 2025 the Supreme Court struck down the exemption that the 29 January 2025 amendment had given industrial sheds, schools, colleges and educational hostels, and upheld the rest of that amendment.
  • The line is measured on built-up area across all covered floors, including basements and service areas, which is wider than the FSI built-up area a planning sanction or a MahaRERA filing reports.
  • On the MahaRERA register as updated on 7 October 2026, 3,471 of 52,937 projects (6.6 percent) file more than 20,000 square metres of FSI built-up area, rising to 11.1 percent of 2026 registrations to date, and that count understates the projects over the clearance line.

Anita's parcel sits under the line, on one measure

Anita Rao (illustrative, as our stories always are) heads business development at a mid-size developer, and this quarter she is sizing a Pune parcel. The architect's first scheme puts the FSI built-up area at 19,200 square metres, under 20,000. The same scheme carries a basement of 3,600 square metres and a stilt floor for parking, neither of which consumes FSI. On the covered-area measure, the scheme is past the line.

Her firm bids land at the number that survives a four-quarter slippage stress. So the question is concrete: does the clearance go into that stress, as months of appraisal before construction can start, or does the scheme get redrawn to stay under the line on the measure that counts? Everything turns on which measure that is.

Names and numbers in this story are illustrative.

The clearance in one paragraph, and an analogy

Environmental clearance is the prior permission the EIA Notification, 2006 requires before construction work or preparation of land starts on a project listed in its schedule. Buildings enter the schedule by size. The closest business analogy is a tax audit threshold, which is read on gross turnover and not on the profit you report. A planning sanction works with the area that consumes FSI, the way a tax return works with taxable income. The clearance line reads the whole covered building, the way a turnover test reads every rupee through the till.

How the line works, and what the 2025 ruling changed

Item 8(a) covers building and construction projects of 20,000 to under 1,50,000 square metres of built-up area. Item 8(b) covers townships and area development projects of 50 hectares or more, or 1,50,000 square metres or more of built-up area. Both are Category B: the State Expert Appraisal Committee appraises the proposal, filed on Form 1 and Form 1A with conceptual plans, and the State Environment Impact Assessment Authority decides. Appraisal decisions, citing paragraph 7(i) III, stage (3)(d) of the notification, record that item 8 projects skip the public consultation stage. For Maharashtra, the Environment Ministry constituted the SEIAA and three dedicated SEACs by a notification of 10 June 2024, as its answer in the Rajya Sabha on 13 March 2025 recorded.

The amendment of 29 January 2025 (S.O. 523(E)) did three things that matter here. It declared the notification's location-based general conditions inapplicable to items 8(a) and 8(b), which keeps them with the state authority. Through a Note 1 to item 8(a), it exempted industrial sheds, schools, colleges and hostels for educational institutions from prior clearance, subject to conditions such as waste management and rainwater harvesting. And it clarified what built-up area means. The same Rajya Sabha answer reported that while a Supreme Court stay was in force, 145 building, township and area development proposals from Maharashtra had been submitted at the Central level instead.

On 5 August 2025, in Vanashakti v. Union of India, a bench led by Chief Justice B.R. Gavai struck down Note 1 and upheld the rest of the amendment. The holding in one sentence: construction of more than 20,000 square metres affects the environment whatever the building is used for, so exempting some kinds of building from appraisal was arbitrary.

For a housing developer the headline changed less than it seemed, because residential buildings were never in Note 1. What the judgment settled for housing is that item 8 proposals are appraised at the state, and that the amended definition of built-up area stands.

What counts toward the line

The 2006 schedule measured covered construction by its covered area. Commentary on the 2025 amendment describes the clarified definition as the covered area on all floors, including basements and service areas. That is a wider measure than the one planning rules use. Under the UDCPR, FSI is computed on the outer periphery of construction floor by floor, and Regulation 6.8 lists what stays outside it, parking stilts and podiums used only for parking among them, while basements fall on two different lists. A sanctioned plan's FSI statement therefore reports a smaller number than the clearance line reads.

The older wording, which said only covered construction, left room for argument about exactly these floors. The 2025 wording narrowed that room, and a scheme close to the line should be measured on it.

Warning

Do not plan a scheme to the FSI figure. The areas most likely to carry a project across 20,000 square metres are the ones FSI rules leave out: basements, parking floors and service floors. Treat the FSI built-up area as the floor of the estimate, have the environmental consultant total the covered area on the final drawings, and decide the clearance question before the land price is fixed.

Where the clearance sits in the sequence

From the area statement to a clearance on file
  1. 1

    1. Total the covered area

    Every floor, basements and service areas included, not only the area that consumes FSI.

  2. 2

    2. Place the project

    20,000 to under 1,50,000 square metres is item 8(a); 50 hectares or 1,50,000 square metres or more is item 8(b).

  3. 3

    3. Apply as Category B

    Form 1, Form 1A and conceptual plans, filed for the state authority.

  4. 4

    4. SEAC appraises, SEIAA decides

    No public consultation stage for item 8 projects.

  5. 5

    5. No work before the clearance

    The requirement is prior clearance, before construction work or preparation of land starts.

  6. 6

    6. Submit it to the planning authority

    UDCPR Regulation 3.1.5 asks for the clearance certificate as the Environment Ministry prescribes.

Source: EIA Notification, 2006, items 8(a) and 8(b), as amended on 29 January 2025; UDCPR Regulation 3.1.5

An integrated township goes further under the UDCPR: its master layout is approved on condition that no work starts without the clearance, which is then submitted with the building permission application. Mumbai works under its own code, so check which rulebook governs the plot first.

MahaRERA comes after. The registration application carries the approvals and the commencement certificate, but the form has no environmental clearance field. A promoter may upload the clearance among the project's documents, but the register does not ask for it by name.

What the register shows about projects near the line

The filings cannot say which projects needed a clearance, but they can say how many file large schemes. On the MahaRERA register as updated on 7 October 2026, 52,937 published projects file a permissible FSI built-up area that passes a sanity check against their plot area. Of those, 3,471 (6.6 percent) file more than 20,000 square metres, and 80 file 1,50,000 square metres or more. The share roughly doubled between 2017 registrations and 2026's to date.

Registrations filing more than 20,000 sq m of FSI built-up area, by registration year(share of projects filing a usable FSI built-up area)
20175.6% (787 of 14,131)
20226.6% (376 of 5,688)
20237.5% (411 of 5,453)
202410.1% (414 of 4,117)
20259.5% (379 of 3,983)
2026 to date11.1% (309 of 2,783)

Source: ReraGenie analysis of MahaRERA filings, as updated on 7 October 2026; 2018 to 2021 not shown. FSI built-up area leaves out basements, stilts and parking floors, so these shares understate the projects over the clearance line.

The districts with the most are Pune (1,269), Thane (694), Mumbai Suburban (407), Raigarh, MahaRERA's spelling of Raigad (259), and Nagpur (201). Two caveats travel with every one of these figures: the filed number is FSI built-up area, so the true count over the line is higher, and a registration may be one phase of a larger scheme.

The reason the line exists is not small either. The buildings and construction sector accounted for 32 percent of global energy use and 34 percent of global carbon dioxide emissions, by the United Nations Environment Programme's Global Status Report for Buildings and Construction 2024/2025 (March 2025).

Where developers get it wrong

  1. Measuring on the FSI figure. The clearance reads covered area, and the gap is largest on schemes with deep basements and parking floors.
  2. Reading a phase as the project. A registration under the line can belong to a scheme over it, so check which boundary the clearance covers.
  3. Assuming the 2025 amendment exempted housing. Note 1 never covered residential buildings, and it has been struck down.
  4. Preparing the land early. The requirement is prior clearance, before construction work or preparation of land starts.

What the project analysis shows for a parcel near the line

ReraGenie's Rs 2,999 project analysis does not read clearances, because MahaRERA files none. For a parcel like Anita's it does set out the built intensity of the district, filed built-up area over plot area, with the project's position in that distribution and the count stated; the registered projects in the 2 km and 5 km rings around the filed location, with their supply; and the pincode's registrations by year, the micro-market read behind a launch.

To see who sanctions building where a parcel sits, ReraGenie's free district pages show each district's registrations by status and the planning authorities its projects name.

Methodology and sources

  • Register figures: ReraGenie's analysis of the 56,091 published MahaRERA projects, as updated on 7 October 2026. A project is counted where its permissible FSI built-up area falls between 0.05 and 15 times its plot area (52,937 projects). The filed figure is FSI built-up area, which excludes non-FSI areas such as basements, stilts and parking floors, while the clearance line is measured on total built-up area, so every count here understates the projects over the line. A registration may also be one phase of a larger scheme.
  • Law: EIA Notification, 2006 (S.O. 1533 of 14 September 2006), items 8(a) and 8(b), as amended by S.O. 523(E) of 29 January 2025; Supreme Court judgment of 5 August 2025 in Vanashakti v. Union of India; Ministry of Environment, Forest and Climate Change, Rajya Sabha answer of 13 March 2025; UDCPR Regulation 3.1.5 (edition of 30 January 2025).
  • Emissions: United Nations Environment Programme, Global Status Report for Buildings and Construction 2024/2025, March 2025.

This article is educational and not legal advice. Confirm the position for your project with your advocate and the authority concerned.