A construction schedule on RERA Karnataka is something few registers in India file at all. The quarterly update on the newer form lists each project's work items, from earthwork to painting, with a planned start and end and an actual start and end beside each. Read across the 1,647 projects whose latest update carries one, as updated on 12 November 2026, it shows how much finished work kept to plan, how far the rest slipped, and which kind of work slips most. It also shows a trap: the "actual" columns are often filled with dates that have not happened yet.
Key takeaways
- 1,647 RERA Karnataka projects file a construction schedule in their latest quarterly update: 27,745 work items, each with planned and actual dates.
- Of 10,339 items filed as finished by the update date, 46 percent finished on the planned date, 25 percent early and 30 percent late, by a median of 235 days.
- Of 13,699 items whose planned end had passed by the update date, 4,087 were still unfinished, a median of 289 days past plan.
- 7,151 'actual' start dates fall after the update was filed: the column holds forecasts as well as facts.
What the schedule files
The newer form's quarterly update carries a standard list of about 18 work items in three groups. Sub-structure covers earthwork, foundation footings, work up to plinth, basement flooring and retaining walls. Super-structure covers the RCC frame, masonry, plastering, weatherproofing and elevation. Finishing covers flooring and tiling, joinery, electrical, water and sanitary finishing, painting, railings, fire-fighting and landscaping. Each row files a percentage done, a planned start and end, and an actual start and end. Quarterly updates appear on 2,286 published registrations, and 1,647 latest updates carry the schedule. Where else the update's figures sit on the page is in reading a RERA Karnataka quarterly update.
The trap in the actual columns
Before counting anything, the "actual" columns have to be tested, and they fail a simple test. An actual date should lie on or before the day the update was filed. 7,151 of the 27,745 actual start dates lie after it, 6,751 of them on items filed as 0 percent done. And 6,849 actual end dates sit on items that are not 100 percent done. So promoters fill the actual columns with expected dates as well as achieved ones. A second sign: on 9,921 items both actual dates are identical to the planned ones, which is either remarkable punctuality or a planned date copied across.
The figures below therefore count an item as finished only when it is 100 percent done and its actual end date is on or before the update's own filing date, and count it as overdue only when its planned end has passed and it is filed as less than 100 percent done.
How finished work compares with plan
Source: ReraGenie analysis of construction schedules in RERA Karnataka quarterly updates, as updated on 12 November 2026; an item counts as finished when 100 percent done with an actual end on or before the update's filing date
46 percent of finished items ended on the planned date, 25 percent early and 30 percent late. The late ones were not marginally late: their median was 235 days past plan, and 982 ran more than a year over. The share on the planned date is high enough to suggest that some of it is the copied-date effect above rather than punctuality; a developer reading a competitor's schedule should treat "on the planned date" as the promoter's statement.
Where the slip is
The three groups behave differently. Sub-structure work is filed on plan most often, 2,735 of 4,925 finished items. Super-structure is the most evenly split, 1,450 on plan, 1,106 late and 1,030 early of 3,586. Finishing works are the one group where early beats late, 794 against 502 of 1,828, which fits promoters re-planning finishing once the frame is up.
The unfinished side tells the other half. Of the 13,699 items whose planned end had passed by the update date, 4,087 were still below 100 percent, a median of 289 days past plan. Super-structure accounts for the most of them, 1,755, ahead of sub-structure (1,296) and finishing (1,036). 875 of the 1,534 projects with any item past its planned end had at least one such item unfinished.
The schedule is the promoter's own plan, filed quarterly and revisable. A promoter can re-plan an item, and the next update shows only the new dates; the register keeps the latest four quarters on the page, so keep your own copy of each update if you are tracking a project over years.
Reading one project's schedule
For a single project, read three things in order. First, the overdue items: rows whose planned end has passed and whose percentage is below 100. Second, the super-structure group, because the frame sets the pace for everything after it. Third, the planned end of the last finishing item against the project's filed completion date: if finishing is planned to end after the date the registration is valid until, the schedule itself says an extension is coming. How the completion date and extensions are read is in what RERA Karnataka's status words mean.
An analogy: a train timetable with the arrivals filled in early
The schedule is a timetable with a column for actual arrivals, and some stations have filled in the arrival time before the train got there. The scheduled times are still useful, and so are the arrivals that have already happened. The skill is telling the two apart, which here means reading the percentage done and the filing date beside every actual date.
Raghavendra watches his developer's schedule
Names and numbers in this story are illustrative. Raghavendra's cousin had signed a joint development in Bengaluru Rural three years earlier, for a share of the flats. When she asked how the work was going, Raghavendra opened the latest quarterly update for her. The schedule showed the RCC frame planned to finish in March 2026, filed at 80 percent in October, with an actual end date of December 2026 already typed in. Raghavendra pointed out that the date was a forecast, not a fact, and that the last finishing item was planned for two months after the project's filed completion date. She raised both with the developer before the next landowners' meeting.
What ReraGenie's free page shows
ReraGenie's free Karnataka page shows the completion date and every extension, how many units are recorded sold or booked out of the total, the construction stage furthest along, the named landowners, the cost lines, the complaints count and the full list of filed documents. The full schedule is in the quarterly update on the project's page on the RERA Karnataka portal. A Karnataka buyer report is on sale for most projects, and new-registration alerts are free; the project watch covers MahaRERA projects only for now. Find a project from the Karnataka project list, and read what quarterly reports carry in general in quarterly progress reports explained.
The one-line summary
Karnataka's schedules show three in ten finished items running late, by most of a year, and three in ten overdue items still open: count an actual date only when the work is done and the date is before the update was filed.
Looking at a project in Karnataka?
ReraGenie publishes a free page for every RERA Karnataka registration it covers: the filed dates, the approvals, the documents and the promoter's other registrations on the same register. A Karnataka buyer report is on sale for most projects, and new-registration alerts are free; the project watch covers MahaRERA projects only for now.
Browse Karnataka projectsCreate a free account to keep a shortlist you can open on any device.