In May 2026, MahaRERA issued show-cause notices to 8,212 projects that had missed a quarterly progress report deadline, 2,311 of them in Pune, Punekar News reported. Even a project that files on time describes itself as it stood at the end of the last quarter, in the promoter's own percentages. A site visit checklist for a flat exists to close that gap: it sets what you see on the ground against what the latest filing says, and it covers the things no filing records at all, such as the road to the gate, the water, the drains and the plot next door.
Key takeaways
- A MahaRERA quarterly filing reports each building's progress on eleven construction activities and the project's common works as they stood at the end of the last quarter; it says nothing about the road outside, the city's water supply or the plot next door.
- UDCPR Regulation 2.8.3 requires a display board at the site naming the owner, developer and licensed professionals, the survey number, the permission's order number and date, the permitted built-up area, the RERA registration number and the project's QR code.
- Section 11(3)(a) of the RERA Act makes the promoter responsible for making the sanctioned plans, layout plans and specifications available at booking, by display at the site or as the regulations specify.
- Counting the slabs cast from the road and setting them against the filing's slab percentage is the most useful single check a visitor can make.
- In September 2026 residents of one 412-flat Wakad society were hiring nearly 12 private tankers a day, Punekar News reported; water is a question for the ground, because the filing's water supply row covers only the project's own works.
What you need before you go
- The latest filing, on your phone or on paper: for each building, the number of floors and the eleven activity percentages, the common works, and the date of the filing. How to read a project's quarterly filings explains the fields.
- The sanctioned plan, or at least the layout. How to read a sanctioned plan explains the colours, including the green dotted line that marks a road not yet built.
- The brochure, so you can set its pictures against the ground.
- A phone that stamps the date on photographs, and a weekday morning.
The visit, in order
Step 1. The approach road
Go from the nearest main road to the gate the way a resident would, at the hour they would. Note the width, the surface, the turns and whether the road crosses land that belongs to someone else. The filing's internal roads and footpaths row covers roads inside the layout, never the one leading to it.
What you will see: how residents will reach home. Red flag: the only access runs through a private plot, or the brochure shows a wide road that the plan marks green dotted, which means a road that does not yet exist.
Step 2. The gate: the board and the hoarding
UDCPR Regulation 2.8.3 tells the owner or developer to put up a display board at a conspicuous place on the site as soon as the building permission is obtained. It must name the owner, the developer and the licensed professionals, give the survey or city survey number, the order number and date of the permission, the built-up area permitted and the RERA registration number, and, since a December 2021 corrigendum, the project's QR code from the online building permission system. The hoarding beside it is an advertisement, so section 11(2) of the RERA Act requires the registration number and MahaRERA's website on it, and MahaRERA has required a QR code on every advertisement since 1 August 2023. The QR code on every ad shows what to do once you scan it.
These rules are enforced. In July 2024, MahaRERA acted against 628 projects for advertising without their registration number and QR code, 250 of them in the Pune region, with penalties of Rs 88.90 lakh, Storyboard18 reported.
What you will see: a board you can photograph and match against the filing. Red flag: no board, or a registration number on the hoarding that belongs to a different phase from the one being sold.
Step 3. The sales office: the sanctioned plan on the wall
Section 11(3)(a) of the RERA Act makes the promoter responsible, at booking and allotment, for making the sanctioned plans, layout plans and specifications available, by display at the site or at another place the regulations name. The Supreme Court, in Ferani Hotels v. State Information Commissioner (2018), read it as requiring developers to display the plans at the site. Ask to see them.
What you will see: the sanctioned layout, which may differ from the brochure's drawing. Red flag: a sales office that offers only the brochure, or a layout whose towers, open space or roads do not match the sanctioned one.
Step 4. The structure: count the slabs
From the road, count the slabs cast on each tower and look for shuttering on the floor above. Then take the filing's "Slabs of Super Structure" row: on a 20-floor tower, 45 percent means about nine slabs. The filing describes the end of the last quarter, so the ground should be at or ahead of it, never behind. As a yardstick, Active Pune district projects registered since 2024 file a median of 1.23 points of their construction checklist a month (2,750 projects, as updated on 11 October 2026). That figure is computed from the promoters' own current filings rather than any history, and it describes the cohort, not a target for any one project.
What you will see: a slab count you can set against the filed percentage. Red flag: fewer slabs on the ground than the filing implies.
Before the visit, open the project on ReraGenie's free project pages: its construction progress by building puts each tower's filed activities on one screen, so the slab count can be checked on the spot, and its possession timeline shows the first promised date beside the current one.
Step 5. The work: people, machines and material
On a working weekday, count the workers you can see, whether the crane moves, and whether material is arriving. Percentages in a filing say how much was done; only the site says whether anyone is doing it now.
What you will see: a busy site or a quiet one. Red flag: an idle site on a working weekday with no reason in sight, such as heavy rain or a festival. One quiet morning is a question to ask, not a finding.
Go on a weekday morning, and once more after a heavy shower if the season allows. A Sunday visit shows you the sales office; a working day shows you the building site, and the rain shows you the drains.
Step 6. Water and drainage
Ask where the occupied buildings around the project get their water, and look for tankers at their gates. In September 2026 the Pimpri-Chinchwad Municipal Corporation was supplying Wakad and Thergaon on alternate days, and a society federation took a list of 36 affected societies across Wakad, Pimple Saudagar, Tathawade, Thergaon and Punawale to the corporation, Punekar News reported. The filing's "Water Supply", "Storm Water Drains" and "Sewerage" rows describe the project's own internal works, not the city's supply. Look at the roadside drains, standing water and whether the plot sits below the road. If a river or nallah is near, run the flood-line check as well.
What you will see: how the neighbourhood lives with water today. Red flag: tankers at every occupied gate on the lane, or a plot lower than the road it drains towards.
Step 7. The neighbours
Look at what stands on every side and what is being built. A tower rising on the plot your windows would face changes the flat. An open plot may be reserved for a public purpose, and the reserved plot next to you explains what may be built there. Overhead power lines matter too: UDCPR Regulation 3.1.2 keeps buildings, balconies included, a set distance from them. Then ask residents of the nearest occupied building what living there is like.
What you will see: the flat's future surroundings. Red flag: construction next door that the brochure's skyline leaves out.
Step 8. Write it down, and ask in writing
List every difference between the ground and the filing, with dated photographs, and send the questions to the promoter by email. Keep the replies.
- 1
1. Approach road
On the ground: width, surface and whose land it crosses. In the filing: only the internal roads row.
- 2
2. Gate
On the ground: the display board and hoarding. In the filing: the registration number and the permissions to match them against.
- 3
3. Sales office
On the ground: the sanctioned plan on display. In the filing: the plan documents and the building count.
- 4
4. Structure
On the ground: slabs cast per tower. In the filing: the slab row's percentage, as of the quarter's end.
- 5
5. Work
On the ground: workers, crane, deliveries today. In the filing: nothing about today.
- 6
6. Water and drains
On the ground: tankers, roadside drains, the lie of the plot. In the filing: the project's internal works only.
- 7
7. Neighbours
On the ground: what rises next door, power lines, the nearest residents. In the filing: nothing.
- 8
8. Questions
Differences between the two, sent to the promoter in writing.
Source: MahaRERA quarterly filing format (eleven activities per building and the common works); UDCPR Regulations 2.8.3 and 3.1.2; RERA Act sections 11(2) and 11(3)(a)
An analogy: the service book and the test drive
A used car's service book tells you the oil was changed on schedule, and it is worth reading first. It cannot tell you that the brakes pull left or that the road outside the seller's house floods. The filing is the project's service book, sworn and dated. The visit is the test drive, and you need both.
Rohit's shortlist, seen by his brother-in-law
Rohit (illustrative, as our stories always are) could not fly to Pune before he booked, so his brother-in-law visited the three projects on his shortlist one weekday, on a video call, while Rohit kept the filings open on his laptop abroad. Names and numbers in this story are illustrative.
The snag came at the Hinjewadi project. Its filing put the slab row of its tower at 40 percent of 15 floors, about six slabs. From the road the brother-in-law counted four, and the crane did not move in the hour he was there. Rohit wrote to the promoter asking which slabs had been cast and when; no reply had arrived by the time he chose.
The Wakad project's board named the permission's order number and the same registration number as the hoarding, and its slab count matched the filing. The occupied society next door had a tanker at its gate, and its watchman said the corporation's water came on alternate days. Rohit asked the promoter in writing what the project would rely on for water until its connection was made, kept the reply, and booked the Wakad flat. The checks he ran later, such as the 12th slab's demand, he made against the architect's certificate, as checking a builder's demand letter describes.
What the buyer report reads for a visit
The Rs 499 ReraGenie buyer report reads the filing and selected filed documents, and three of its sections speak directly to what a visitor sees:
- Sanctions, units and sales building by building, so you know which tower you are counting and how much of it is filed as sold.
- Construction pace against the district, the project's progress per month beside the median of comparable projects in its district, where at least 20 file the figures.
- Projects within 2 km, the other registrations nearby, which is where the construction next door shows up on paper.
It includes the project's filed documents as a ZIP and a free 90-day project watch. See what the buyer report covers.
The checklist
- Drive the approach road at the hour a resident would.
- Photograph the display board and the hoarding, and match the numbers to the filing.
- Ask to see the sanctioned plan, and compare it with the brochure.
- Count the slabs on each tower against the filing's slab row.
- Note the workers, the crane and the deliveries on a weekday.
- Ask the neighbours about water, and look at the drains.
- Look at every side of the plot, including the sky.
- Send your questions in writing, and keep the answers.
When the keys are near, the same habit carries into the pre-possession inspection.
Methodology and sources
- Filing fields: the MahaRERA quarterly progress format as carried in published project filings, eleven activities per building plus common works.
- Rules: UDCPR (consolidation of 30 January 2025) Regulations 2.8.3 and 3.1.2; RERA Act sections 11(2) and 11(3)(a); Ferani Hotels v. State Information Commissioner, Supreme Court, 2018, as reported.
- Enforcement and water: Punekar News on the May 2026 show-cause notices and on Wakad's water in September 2026; Storyboard18 on the July 2024 advertising action.
- Register: ReraGenie analysis of Active MahaRERA projects registered since 2024, as updated on 11 October 2026.
This article is educational and not legal advice. For a dispute, consult a lawyer who practices before your state's RERA.