The letter is polite and short. The promoter "proposes certain improvements to the layout", the revised plan is "available at the site office", and allottees are requested to sign the enclosed consent at the earliest. Other buyers find out later and less politely, from a column standing where the sanctioned plan showed a doorway, or an extra floor rising on the tower next door. Either way, the question behind every search for builder changed plan after booking is the same: did they need your permission? Under section 14 of the RERA Act, very often they did.

Key takeaways

  • Section 14(1) of the RERA Act requires a promoter to develop and complete the project in accordance with the sanctioned plans, layout plans and specifications approved by the competent authorities.
  • Section 14(2)(i) bars changes to your own apartment without your previous consent, except minor, non-structural changes you asked for or that an authorised architect or engineer recommends and declares to you.
  • Section 14(2)(ii) bars other changes to the buildings or common areas without the previous written consent of at least two-thirds of the allottees other than the promoter, each allottee counting once.
  • In September 2026 the Maharashtra Real Estate Appellate Tribunal penalised the promoters of a Mumbai project 2 percent of the project cost for altering the disclosed sanctioned plans without the allottees' consent.
  • MahaRERA disposed of 6,945 complaints in 2025, 81 percent more than in 2024.

Suresh and Kavita (illustrative, as our stories always are) bought their Pune retirement flat for Rs 95 lakh, without a loan and in Suresh's sole name, in a tower that is now complete with its occupancy certificate. The same MahaRERA registration also covers two more towers, the clubhouse and the internal road that serves the whole layout. Names and numbers in this story are illustrative.

While their own tower was still being built, a one-page consent form arrived from the promoter. It asked allottees to agree to two things at once: moving the clubhouse from the podium to a separate corner of the layout, and adding a floor to one of the two unfinished towers. There was a single signature line for both, and the covering letter called them improvements.

Kavita, a retired bank officer who reads documents before she signs them, asked for something simpler than a viewing at the site office: copies of the revised layout and the sanctioned one, to lay side by side.

What the law actually says

Section 14(1) of the Real Estate (Regulation and Development) Act, 2016 sets the baseline: the promoter must develop and complete the project in accordance with the sanctioned plans, layout plans and specifications approved by the competent authorities. Section 14(2) then says who must agree before any of that changes, and it draws two lines.

Your own flat, clause (i). The promoter may not make additions or alterations to the sanctioned plans, layout plans and specifications, or to the nature of the fixtures, fittings and amenities described for the apartment you agreed to take, without your previous consent. A proviso allows two kinds of minor change without it: minor additions or alterations you ask for, and minor changes necessary for architectural and structural reasons, duly recommended and verified by an authorised architect or engineer after proper declaration and intimation to you.

The Act then closes the obvious loophole. Its explanation says "minor additions or alterations" excludes structural change: an addition to the area or a change in height, the removal of part of the building, the construction, removal or cutting into of a wall, partition, column, beam, joist or floor, a change to or closing of a required means of access, and a change to the fixtures or equipment. A beam dropped through your living room is not minor, whoever signs the recommendation. If the change has cost you area, the carpet area shortfall guide sets out the refund side.

The building and the common areas, clause (ii). Any other alteration or addition to the sanctioned plans, layout plans and specifications of the buildings or the common areas within the project needs the previous written consent of at least two-thirds of the allottees, other than the promoter, who have agreed to take apartments in that building. A second explanation fixes the count: an allottee is one allottee irrespective of the number of apartments booked in his name or his family's. Flats the promoter still holds carry no vote, and an investor with five flats has the same single vote as a retired couple with one.

Two words in that clause do most of the work: previous, and written. A consent collected after the change is built, or read into a buyer's silence, is not what the Act describes. A building RERA does not govern has a parallel restriction in section 7 of MOFA, the state's older flats law; MOFA or RERA explains which law covers yours.

The two-thirds figure will be familiar from project transfers under section 15, and the resemblance is a trap. A transfer needs two-thirds of the project's allottees and MahaRERA's prior written approval; a plan change under section 14(2)(ii) counts the allottees who have agreed to take apartments in the building concerned. A signature on one is not consent to the other. Where a change touches a common area a whole layout shares, such as a clubhouse, ask the promoter in writing which allottees it is counting.

What MahaRERA and the Tribunal have done with it

  • A floor stopped before it was built. In 2020, MahaRERA barred a promoter from constructing an additional floor without the consent of two-thirds of the allottees, rejecting the argument that clauses in the agreements about extra floors were enough.
  • A standard format for the consents. MahaRERA's Circular No. 28 of 2021 set out standard formats for several applications, among them a promoter's application under section 14(2) to correct or amend a registered project, filed with the consent of at least two-thirds of the allottees. A consent form you are handed is, in principle, a document the promoter means to file.
  • A penalty after the fact. On 7 July 2025, MahaRERA found that the promoters of a Mumbai project had violated section 14(2). On appeal the promoters argued that their agreements already allowed development with additional FSI, and in September 2026 the Maharashtra Real Estate Appellate Tribunal held that they had altered the disclosed sanctioned plans without the allottees' required consent, imposed a penalty equal to 2 percent of the project cost, and ordered that the sale proceeds of commercial units built with the additional FSI be apportioned among the allottees.

Where the planning authority fits

A revised plan usually comes with a fresh sanction from the planning authority, and a promoter may present that sanction as the end of the matter. Section 14 does not read that way: clause (1) ties the project to the plans the competent authority approved, and clause (2) adds the allottees' consent before those plans change. Nothing in the section makes the authority's approval of a revision a substitute for the consent.

The best-known illustration comes from another state and another law. On 31 August 2021, in Supertech Ltd v Emerald Court Owner Resident Welfare Association, the Supreme Court ordered the demolition of two Noida towers whose plans had been revised, with the NOIDA Authority's sanction, to raise them from 24 floors to 40, holding among other violations that the revisions breached the Uttar Pradesh apartment law's requirement of the existing flat owners' consent. The towers came down in 2022. The statute was not RERA, but the case shows a court refusing to let a sanction stand in for the consent the law required.

Three kinds of change, compared

The changeExamplesConsent the Act requiresWhere to act, and what to ask for
Inside your own flatA smaller room, a moved kitchen, a column the plan did not show, other fittings than the agreement'sYour previous consent, section 14(2)(i)Object in writing; complain to MahaRERA for restoration, compensation, or a refund if the flat cannot be delivered as agreed
A minor changeA door shifted at your request, or a non-structural adjustment an authorised architect or engineer recommendsNone if you asked; otherwise the architect's or engineer's verified recommendation, declared and intimated to youAsk for the recommendation in writing; a structural change labelled minor still needs your consent
To the building or the common areasAn extra floor, a clubhouse moved, a road rerouted, open space reducedPrevious written consent of at least two-thirds of allottees other than the promoter, one vote each, section 14(2)(ii)Question or decline before signing; if built without consent, a MahaRERA complaint, best filed through the association

An analogy: the group tour

Think of a group tour you booked for your family. The operator may swap the coach for an identical one if its mechanic says the first is unsafe, as long as it tells you. It may not move your family to a smaller room without your agreement. And it may not drop the boat ride everyone paid for, or add a detour to the shared itinerary, unless two-thirds of the travelling parties agree, each booking family getting one vote however many seats it holds. Section 14 is that bargain written into law: your room is yours to agree to, and the itinerary belongs to the group.

What the regulator's docket looks like

We could not find a published count of complaints about plan changes alone, so the useful figure is the forum's overall throughput. By MahaRERA's figures for the year, it disposed of 6,945 complaints in 2025, 81 percent more than the 3,824 of 2024, and 6,916 were still pending. A complaint about a floor not yet built is where an early order matters most, since stopping a change is simpler than undoing one.

MahaRERA complaints disposed, and still pending(complaints)
Disposed in 20243,824
Disposed in 20256,945
Pending, 2025 figures6,916

Source: MahaRERA's figures for calendar 2025, as reported by The Realty Today

What to do this week

If a consent form has arrived:

  1. Do not sign on the day. Ask for the revised plan and the sanctioned one, in copies you keep. How to read a sanctioned plan explains the colours, and the sanctioned plans should also be on the planning authority's website, as this guide to sanctioned plans online sets out.
  2. Ask what exactly changes, in writing: your flat, your building or the shared layout, which clause of section 14 the promoter relies on, and which allottees it is counting.
  3. Ask for one form per change. A form that bundles two changes makes you accept both or neither.
  4. Talk to the other buyers. Two-thirds is a collective threshold, and a buyers' association is how a layout counts itself and speaks once.

If the change is already built:

  1. Photograph it with the date showing, and set it against the sanctioned plan and your agreement, using the model agreement clauses as the checklist.
  2. Write to the promoter citing section 14, as a legal notice to your builder describes, then file a MahaRERA complaint. You can ask for a direction under section 37 to stop or restore the work, compensation under section 18(3), or, where your own flat can no longer be delivered as agreed, withdrawal with a refund and interest under section 18(1).

Every document a promoter has filed for a MahaRERA registration, including the building plan approval with its upload date, is listed free on that project's page at reragenie.com/projects, which is the place to start before you sign anything.

Warning

Never sign a consent for a plan you have not seen in full. The covering letter's word for the change, an improvement or a minor revision, is the promoter's description, not the plan, and your signature on a one-page form becomes the promoter's evidence that you agreed.

What Suresh and Kavita did

Laid side by side, the two plans answered the covering letter. The clubhouse would leave the podium their tower opened onto for a far corner across the internal road, and the extra floor would add flats sharing that road and that clubhouse. Both were changes to common areas, and one signature line asked for both.

They did not sign, and said why in a short letter: they would consider each change separately, once the promoter confirmed which allottees it was counting. Suresh, in whose sole name the flat stands, held the household's one vote, and it would have been one vote even had the flat been booked in both their names. Enough neighbours asked the same questions that the consent drive fell short, and the promoter kept the sanctioned layout.

It did not build the clubhouse there either. The registration has since lapsed with the clubhouse, the road and the two towers unfinished, and the association in which Kavita serves as secretary is working through what section 8 offers when a promoter walks away. The consent they withheld did not finish the project, but it kept the layout they bought into intact on paper, which is the plan the association can hold any completion to.

What the filings add

On ReraGenie's free project pages, every filed document is listed with its upload date, and the permission chain shows whether the layout approval and building plan approval slots hold a document and when it was uploaded: an upload, not proof of what was approved. For any covered Maharashtra project, the Rs 499 buyer report adds:

  • Sanctions, units and sales building by building, so you know what each tower holds on the filing before a revision proposes more.
  • The project's filed documents as a ZIP, including the approvals the promoter uploaded, to lay beside a revised plan from a consent form.
  • A free 90-day project watch, which emails you when the project's filing changes.

The one-line summary

Your flat changes only with your consent, and your building or its common areas only with two-thirds of the allottees, one vote each, given in writing before the change: ask for the sanctioned plan beside the revised one, ask who is being counted, and treat the form as the vote it is.

This article is educational and not legal advice. For a dispute, consult a lawyer who practices before your state's RERA.