An APRERA complaint takes one of two routes. A complaint that a promoter or agent broke the Act goes to the authority in Form M; a claim for interest or compensation, for delay, a defect or a refund, goes to the adjudicating officer in Form N. Each carries a fee of Rs 1,000 under Andhra Pradesh's 2017 rules. What makes Andhra Pradesh different is the evidence: a project's own page on the register can carry the promoter's declared delay in months, with its reason, and the money it has collected against the money it has spent. This guide explains the two routes, what to put in the complaint and what happens after the order.

Key takeaways

  • A complaint about a breach of the Act goes to APRERA in Form M; a claim for interest or compensation goes to the adjudicating officer in Form N; each carries a Rs 1,000 fee under the Andhra Pradesh rules of 2017.
  • Interest for delay is the State Bank of India's highest marginal cost of lending rate plus 2 percent, under the rules as amended in June 2023.
  • An APRERA project page under development files whether the project is delayed, by how many months and why, in the promoter's own words, which is evidence a buyer can attach.
  • APRERA's approved projects list held 7,229 projects when ReraGenie read it on 29 October 2026, and the authority had 248 registered agents when PTI reported its call on unregistered agents in August 2025.
  • From 1 April 2026, APRERA said, projects that never registered face penalties of up to 10 percent of their cost and publication of their names.

The two routes

Form M, to the authorityForm N, to the adjudicating officer
What it is forA breach of the Act, the rules or the regulations by a promoter, an agent or a buyerInterest and compensation under sections 12, 14, 18 and 19 of the Act
Typical casesSelling without registration, changing the plan without consent, not filing updates, an unregistered agentDelay in possession, a refund on withdrawal, compensation for a defect or a false statement
FeeRs 1,000Rs 1,000
Who decidesThe authorityThe adjudicating officer

The split comes from the Act: section 31 lets anyone complain to the authority, and section 71 gives claims for compensation to an adjudicating officer. If what you want is money for a delay, Form N is the route; if you want the promoter made to comply or penalised, Form M is. Many cases raise both, and can be filed both ways.

Filing, step by step

An APRERA complaint, from filing to order
  1. 1

    1. Register on the portal

    Complaint registration on rera.ap.gov.in.

  2. 2

    2. Choose the form and pay

    Form M to the authority or Form N to the adjudicating officer, with the Rs 1,000 fee.

  3. 3

    3. Attach the evidence

    The agreement, the receipts, the project's registration number and a saved copy of its page.

  4. 4

    4. Notice and reply

    The promoter is sent the complaint and given time to answer.

  5. 5

    5. The hearing

    Both sides are heard, on the documents first.

  6. 6

    6. The order

    Directions or a penalty from the authority; interest and compensation from the officer; or a reasoned dismissal.

Source: ReraGenie, from sections 31 and 71 of the RERA Act and the Andhra Pradesh rules of 2017

The evidence the register gives you

Andhra Pradesh's register files things most registers do not, and three of them are evidence:

  • The declared delay. Once a project reports itself under development, its page answers "Is the project delayed", gives the number of months, and states the reason. That is the promoter's own statement, filed with the regulator. Save the page on the day you file.
  • Money in and money out. The same block files the total money collected from allottees, the total spent on development and the balance in the separate account. A large gap between money collected and money spent, on a project that is also late, is a question for the hearing.
  • Your flat's row. The page's table of every flat gives the carpet area and the other areas of each unit. If the flat handed over is smaller than its filed carpet area, that row is your starting point. Carpet area shortfall covers what to claim.

Two cautions. The status word on the list is not a standing, so do not rely on "Under Development" to show a project is on time; rely on the dates. And on a project still listed as New Project, the money and delay block is often absent, so the dates in your agreement and on the list are the evidence. How to find each part of the page is in how to check a project on the APRERA portal.

Tip

For a delay claim, work out the interest month by month on each instalment you paid, from the date in your agreement, at SBI's highest marginal cost of lending rate plus 2 percent, and attach the table to Form N with a saved copy of the project page showing the declared delay.

When the project never registered

Selling in a project that should have registered breaks section 3 of the Act, and the remedy runs to the authority in Form M. APRERA's circular of 29 December 2025 offered unregistered projects a concession for registering late until 31 March 2026, and said that from 1 April 2026 it would impose penalties of up to 10 percent of project cost under section 59(1) and publish the names of projects still unregistered. In June 2025 it had warned buyers against pre-launch offers and against agents selling in unregistered projects, which section 10 of the Act forbids. A buyer who paid in an unregistered project should file early: the penalty is the authority's to impose, but the record of who complained, and when, is the buyer's.

After the order, and the appeal

An order is not yet money. If the promoter does not pay, section 40 of the Act lets the amount be recovered as arrears of land revenue, through the district administration. How that machinery works is in recovery warrants, written for Maharashtra but built on the same section of the Act.

Either side can appeal within 60 days of the order under section 44. The state constituted the Andhra Pradesh Real Estate Appellate Tribunal in 2019; reports since have questioned whether it has been sitting, so confirm with APRERA before you plan on an appeal. A promoter's appeal is heard only after it deposits at least 30 percent of a penalty, or the whole amount ordered to the buyer, under section 43(5).

An analogy: a written confession in the file

The declared delay on an APRERA page is like a written confession already in the court file. The promoter wrote it, filed it with the regulator and signed off on its professionals' certificates. A buyer who saves it does not have to prove the delay; the hearing can move straight to how much is owed.

Lakshmi's nephew files Form N

Names and numbers in this story are illustrative. Lakshmi's nephew in Visakhapatnam had bought the 2BHK whose page, a year earlier, declared an eight-month delay for "labour shortage". The new date passed too. He filed Form N with his agreement, his eleven receipts, a table of interest on each instalment from the agreement's date, and two saved copies of the project page a year apart: the first declaring eight months of delay, the second fourteen, with money collected rising faster than money spent. The officer's order awarded interest at the rules' rate. Lakshmi kept a note of the lesson for her own plot: save the page on the day you pay, and every few months after.

What ReraGenie's free page shows

ReraGenie lays each APRERA registration it publishes out on a free page, in the same shape as its pages for other states: the dates the promoter filed, the promoter and the professionals who certify the project, and the documents filed with the registration, and it never prints the register's status word as a standing. Open a project from the Andhra Pradesh project list. The register's own page is still the record of the money and delay figures, and saving it with a date is the habit that wins complaints. What the regulator registers and enforces is in what is APRERA, the general mechanics of a RERA complaint are in how to file a RERA complaint, and the whole purchase is in buying property in Andhra Pradesh.

The one-line summary

Form M to make a promoter comply, Form N to be paid, Rs 1,000 each, filed online with the agreement, the receipts and saved copies of the project page, whose declared delay and money figures are the promoter's own evidence against it.

This article is educational and not legal advice. For a complaint, consult a lawyer who practices before APRERA.

Looking at a project in Andhra Pradesh?

ReraGenie publishes a free page for every APRERA registration it covers: the filed dates, the approvals, the documents and the promoter's other registrations on the same register.

Browse Andhra Pradesh projects

Create a free account to keep a shortlist you can open on any device.